Work Completed this Week

  • Poured concrete curb & gutter along Herrick Road
  • Poured concrete ADA ramps at intersection of Herrick Road & Cowley Road
  • Poured concrete sidewalk along Herrick Road
  • Removed remaining sidewalk, curb & gutter and 1 driveway on Herrick Rd at St. Mary’s Church

Upcoming Work Planned Next Week

  • Pour concrete driveway on Herrick Road at St. Mary’s Church
  • Pour concrete sidewalks and ADA ramps on Herrick Road
  • Pour concrete curb & gutter along Forest Avenue
  • Pour concrete ADA ramps along Forest Avenue
  • Pour concrete sidewalk along Forest Avenue
  • Remove curb & gutter along Barrypoint Road