Street Paving Update - May 24, 2019

Herrick Road Repaving Photo - 5-24-2019

Work Completed this Week

  • Removed sidewalk, curb & gutter on Herrick Road
  • Removed existing ADA ramps at intersection of Herrick Road & Cowley Road

Upcoming Work Planned Next Week

  • Pour concrete curb & gutter along Herrick Road
  • Pour concrete ADA ramps at intersection of Herrick Road & Cowley Road
  • Pour concrete sidewalk along Herrick Road
  • Remove remaining sidewalk, curb & gutter and 1 driveway on Herrick Road at St. Mary’s Church
  • Pour concrete driveway on Herrick Road at St. Mary’s Church