Selborne Road Driveway Apron Resized for Trending

Work Completed this Week

  • Completed backfilling gap between new curb and existing pavement with stone on North side of Selborne Road
  • Opened all driveways for access on North side of Selborne Road
  • Saw cut pavement on South side of Selborne Road
  • Began removal of existing curb and gutter and driveway aprons on South side of Selborne Road
  • Began grading for curb and gutter installation on South side of Selborne Road

Upcoming Work Planned for Next Week

  • Complete removal of curb and gutter and driveway aprons on South side of Selborne Road
  • Adjust drainage structures on South side of Selborne Road
  • Begin installation of curb and gutter on South side of Selborne Road
  • Begin preparation for concrete driveway aprons on South side of Selborne Road

See All Construction Updates Here
Facebook Twitter Email

Other News in E-Flash

ComEd Powering Lives color logo

ComEd News

Posted on: August 6, 2020
COVID-19 Image - 3-13-2020

August 5, 2020 COVID-19 Update

Posted on: August 6, 2020

Cori's Virtual Tri

Posted on: July 29, 2020
Census 2020 Graphic Resized for Trending

2020 Census Update

Posted on: July 30, 2020
Senior in Mask

June 16 Census Update

Posted on: June 16, 2020