[ARCHIVED] Selborne Road Construction Update for June 5

6-5-2020 - Geogrid and Stone

Work Completed this Week

  • Completed asphalt surface removal on Selborne Road and Parkway Road.
  • Removed concrete base on Selborne Road from Nuttall Road through the intersection at Southcote Road.
  • Placed geogrid to stabilize the soil subgrade and placed 9-inches of stone sub-base on Selborne.

Upcoming Work Planned Next Week

  • Continue removal of concrete base and placement of geogrid and stone sub-base on Selborne Road.

See All Construction Updates Here
Facebook Twitter Email

Other News in E-Flash

ComEd Powering Lives color logo

ComEd News

Posted on: August 6, 2020
COVID-19 Image - 3-13-2020

August 5, 2020 COVID-19 Update

Posted on: August 6, 2020

Cori's Virtual Tri

Posted on: July 29, 2020
Census 2020 Graphic Resized for Trending

2020 Census Update

Posted on: July 30, 2020
Senior in Mask

June 16 Census Update

Posted on: June 16, 2020