Posted on: August 11, 2017

Project Update: First Division Sewer Separation - August 11, 2017

Work Completed This Past Week

  • Completed storm sewer and sanitary sewer in Phase 3 (Scottswood - West).
  • Began storm sewer installation on Fairbank Road in Phase 4.

Upcoming Work Planned Next Week

  • Continue storm sewer and installation in Phase 4 project limits.
    • Aug 14, 2017 Intersection of Coonley and Fairbank will be closed.
  • Pavement patching and concrete restoration in Phase 2 and 3 on Bloomingbank and Scottswood - West.

Construction Updates
Facebook Twitter Google Plus Email

Other News in E-Flash

Riverside Logo with Tower in the Background

Hydrant Flushing in Riverside

Posted on: August 22, 2017

Riverside Farmers' Market This Week!

Posted on: August 22, 2017

Cori's Kids Triathlon Results

Posted on: August 19, 2017
Police Car with the door open

RPD Labor Day Traffic Enforcement

Posted on: August 16, 2017
Three Explorers next to a Back to School Sign

Riverside Police Community Advisory

Posted on: August 10, 2017
Riverside Logo with Tower in the Background

Volunteers Needed

Posted on: July 24, 2017
Mollies Public House - Forest Avenue

Forest Avenue Detour Returns

Posted on: July 11, 2017
Construction Map 6-29-2017

New Traffic Patterns and Detours!

Posted on: June 30, 2017
Soapy Water with the Word Wash

Keeping Refuse Containers Clean

Posted on: May 31, 2017
Mollies Public House - Forest Avenue

Forest Avenue Update

Posted on: May 24, 2017
Road-closed-signs-detour-traffic

Harlem Avenue Resurfacing

Posted on: April 24, 2017

KinderKids 2017-2018 Registration

Posted on: April 13, 2017

Hen & Beekeeping Pilot Programs

Posted on: December 29, 2016