News Flash

Posted on: April 23, 2019

Street Paving Update - April 19, 2019

Herrick Road Repaving Project Week 1 - 4-23-2019

Weekly Report #1 - April 19, 2019

Work Completed this Week

  • Mobilized to Herrick Road.
  • Investigated all existing drainage structures.
  • Sawcut removal limits for drainage structure replacement on Herrick Road and Forest Avenue.

Upcoming Work Planned Next...

Read on...

View All Updates Here Construction Updates
Posted on: April 22, 2019

Construction Update - April 19, 2019

Commuter Lot 1 Green Parking Lot April 16

Work Completed this Week

  • Installed final course of aggregate prior to brick paver installation with fine grading and roller compaction.
  • Installed remaining curb and gutter and concrete edge restraint within parking lot.
  • Removed sidewalk along north Bloomingb...
Read on...

View All Updates Here Construction Updates
Posted on: April 12, 2019

Construction Update - April 12, 2019

Rain_Garden_Parking_Lot_1_in_Progress

Work Completed this Week

  • Installed coarse aggregate subgrade in parking lot.
  • Installed remaining storm sewer and observation wells.
  • Final grade in Rain Garden 1 and Rain Garden 2.
  • Installed seed and blanket along the rain garden.
  • Began concrete curb installati...
Read on...

View All Updates Here Construction Updates
Posted on: April 5, 2019

Construction Update - April 5, 2019

4-5-2019 - Lot 1 Photo 3 Resized for Trending

Work Completed this Week

  • Installed electrical conduit, bollard foundations and light pole foundations.
  • Installed wire span poles and foundations.
  • Installed storm sewer and open manhole connections to the rain garden.
  • Removed existing drainage structures.

Upcom...

Read on...

View All Updates Here Construction Updates
Posted on: April 3, 2019

2019 Road Construction

Road-closed-signs-detour-traffic-temporary

The Village's 2019 street resurfacing projects are scheduled to begin on Herrick Road on April 15.   Forest Avenue and Barrypoint Road will also be resurfaced.  IDOT has awarded the resurfacing contract to Lindahl Brothers of Bensenville...

Read on...

View All Updates Here Construction Updates
Posted on: March 29, 2019

Construction Update

Truck-Working-Commuter-Lot-1-3-27-2019

Work Completed this Week

  • Completed removals of parking lot existing subbase down to final subgrade.
  • Completed removals and grading for subgrade elevations for Rain Garden 1 and Rain Garden 2.

Upcoming Work Planned Next Week

  • Remove existing parking lot drainag...
Read on...

View All Updates Here Construction Updates
Posted on: March 22, 2019

Construction Update

3-22-2019 Lot 1 Photo

Work Completed the Past Week

  • Work began on March 16, 2019.
  • Installed temporary lighting in Riverside Swim Club parking lot.
  • Installed temporary striping/numbering in Riverside Swim Club parking lot and additional train station parking.
  • Installed tree protecti...
Read on...

View All Updates Here Construction Updates