Posted on: June 23, 2017

Project Update: First Division Sewer Separation - June 23, 2017

First Division Sewer Separation Project - Progress Report

June 23, 2017

Work Completed This Past Week

  • Storm sewer installation continued along Fairbank and Barrypoint in Phase 2 project limits.
  • Barrypoint Detour was installed.
  • Asphalt patching restora...
Read on...

Posted on: June 20, 2017

ROAD CLOSED: Barrypoint Road

ROAD CLOSURE:  Barrypoint Road will be closed to all through traffic starting tomorrow June 21 – June 30.  Please follow posted detours.  

Southbound traffic will be re-routed as follows:  Bloomingbank to Scottswood to B...

Read on...

Detour Map
Posted on: June 16, 2017

Project Update: 2017 Street Improvements

Northwood:

  • Concrete saw cutting has been performed on both sides of the street.
  • Concrete curb, sidewalks, and driveway aprons on both sides of the street have been removed.

Evelyn:

  • Concrete saw cutting has been performed on both sides of the street.
  • Concrete c...
Read on...

Additional information.
Posted on: June 16, 2017

Project Update: First Division Sewer Separation

Entire Construction Area:

  • All trees within construction limits have been pruned as needed.
  • Tree protection has been established.
  • Perimeter erosion barriers have been installed at the outfall locations.

Phase 1:  

  • All sanitary service and water main ad...
Read on...

Posted on: June 16, 2017

Project Update: Train Station Roof Replacement

Clay roof tiles have been removed.  Tiles suitable for reuse have been stored and replacement tiles have been ordered from the manufacturer.  The projected delivery of replacement tiles is August.  New valley flashings have been...

Read on...

Posted on: June 9, 2017

2017 Street Improvements

Road-closed-signs-detour-traffic-temporary

The Village is pleased to announce that the 2017 Street Paving Project is scheduled to begin on Monday, June 12, 2017.  The scheduled work will involve the resurfacing of roadways, drainage structure repairs (where necessary), new curb and gutter ...

Read on...

Read the Construction Notice here!
Posted on: June 9, 2017

Weekly Construction Update - June 9, 2017

First Division Sewer Separation Project

Progress Report

June 9, 2017

Work Completed This Past Week

  • Contractor completed installation of new storm sewer within Phase 1.
  • Contractor began installation of new storm in Phase 2 starting with the installation of the ...
Read on...

Posted on: May 26, 2017

Weekly Construction Update - May 26, 2017

First Division Sewer Separation Project

Progress Report

May 26, 2017

Work Completed This Past Week

  • Contractor continued sanitary service replacements within Phase 1 limits.
  • Contractor completed installation of sanitary manholes and connections within Phase 1.
  • C...
Read on...

Posted on: May 24, 2017

Forest Avenue Update

Mollies Public House - Forest Avenue

Forest Avenue has reopened to two-way traffic and parking is now available on both sides of the street.

The MWRD project has relocated to Riverside Road.  Please use caution when crossing the BNSF railroad tracks in the center of town. Traffic is ...

Read on...

Posted on: May 19, 2017

1st Division Sewer Separation Project Update

First Division Sewer Separation Project

Progress Report

May 19, 2017

Work Completed This Past Week

  • Contractor continued sanitary service replacements within Phase 1 limits.
  • Contractor began installation of new sanitary manholes and new storm sewer line within ...
Read on...

Posted on: May 17, 2017

Downtown Construction Traffic Alert for Motorists & Commuters

Road-closed-signs-detour-traffic

The MWRD sewer lining project will be shifting their staging from Forest Avenue to Longcommon on Thursday, May 18th. The new staging location will be on the east side of Longcommon just north of the BNSF railroad tracks. The easternmost northbound lane of...

Read on...

For a full-sized map of affected construction area
Posted on: May 12, 2017

Weekly Construction Update - May 12

Road-closed-signs-detour-traffic

First Division Sewer Separation Project - Progress Report - May 12, 2017

Work Completed This Week

  • Contractor completed installation of tree protection fencing.
  • Contractor began installations of sanitary service adjustments and replacements ...
Read on...

Posted on: May 10, 2017

Construction Update - May 10

Road-closed-signs-detour-traffic

Pavement striping on Quincy and Longcommon will be installed May 10th.  Please allow additional time and utilize caution while driving in the area and obey any posted no parking or temporary detours signs and any flaggers.  The stamped a...

Read on...

Posted on: May 5, 2017

Weekly Construction Update - May 5

First Division Sewer Separation Project

Progress Report

May 5, 2017

Work Completed This Past Week

  • Contractor installed perimeter erosion barrier along four outfall work areas.
  • Contractor removed trees, canopy pruned trees, and root pruned trees.
  • Contractor inst...
Read on...

Posted on: April 27, 2017

2017 Construction Projects

Various large scale construction projects are underway this year in and around Riverside including Village, MWRD and IDOT projects. For details on these various projects see below.

FIRST DIVISION SEWER SEPARATION PROJECT – VILLAGE OF RIVERSIDE 

Thi...

Read on...