Posted on: August 11, 2017

Project Update: First Division Sewer Separation - August 11, 2017

Work Completed This Past Week

  • Completed storm sewer and sanitary sewer in Phase 3 (Scottswood - West).
  • Began storm sewer installation on Fairbank Road in Phase 4.

Upcoming Work Planned Next Week

  • Continue storm sewer and installation in Phase 4 project limits....
Read on...

Construction Updates Construction Updates
Posted on: August 4, 2017

Project Update: First Division Sewer Separation - August 4, 2017

Work Completed This Past Week

  • Completed storm sewer and sanitary sewer installation on Bloomingbank (Phase 2).
  • Installed topsoil and seed in Phase 2 and Phase 3 areas. Prepared areas for sod.
  • Continued storm sewer installation in Phase 3 through Scottswood C...
Read on...

Construction Updates Construction Updates
Posted on: July 28, 2017

Project Update: First Division Sewer Separation - July 28, 2017

Work Completed This Past Week

  • Installed asphalt patching on Barry Point, Fairbank, and Scottswood (East)
  • Installed storm sewer and sanitary sewer on Bloomingbank (Phase 2)

Upcoming Work Planned Next Week

  • Install storm sewer and sanitary sewer on Bloomingbank ...
Read on...

Construction Updates
Posted on: July 21, 2017

Project Update: First Division Sewer Separation - July 21, 2017

Progress Report

July 21, 2017

Work Completed This Past Week

  • Installed curb and gutter and sidewalk on Fairbank, Barrypoint and Scottswood (East)
  • Installed asphalt patching on Barrypoint and Scottswood (East)
  • Prepared for asphalt patching on Scottswood (East) a...
Read on...

Construction Updates
Posted on: July 21, 2017

Project Update: First Division Sewer Separation - July 21, 2017

Progress Report

July 21, 2017

Work Completed This Past Week

  • Installed curb and gutter and sidewalk on Fairbank, Barrypoint and Scottswood (East)
  • Installed asphalt patching on Barrypoint and Scottswood (East)
  • Prepared for asphalt patching on Scottswood (East) a...
Read on...

Construction Updates
Posted on: July 14, 2017

Project Update: First Division Sewer Separation - July 14, 2017

First Division Sewer Separation Project

Progress Report

July 14, 2017

Work Completed This Past Week

  • Completed storm sewer installation in Phase 3 on Scottswood (East)
  • Completed Fairbank storm sewer installation (Phase 2)
  • Continued storm sewer installation throu...
Read on...

Concstruction Updates Construction Updates
Posted on: July 14, 2017

New Traffic Patterns and Detours in the First Division!

First Division Sewer Separation

Work is progressing on the First Division Sewer Separation Project. Occasional road closures and detours are required. Please follow posted detours and observe posted speed limits in the construction zone at all times. Please also consider taking an alter...

Read on...

Construction Updates Construction Updates
Posted on: July 11, 2017

Forest Avenue Detour Returns

Mollies Public House - Forest Avenue

The Forest Avenue detour to Pine Avenue has been reinstituted by the MWRD sewer lining contractor to facilitate manhole rehabilitation.  The process is expected to take approximately six weeks and be completed during mid-August. The manhole rehab...

Read on...

Construction Updates
Posted on: July 7, 2017

Project Update: First Division Sewer Separation - July 7

Work Completed This Past Week

  • Storm sewer installation continued in Phase 3 on Scottswood (East).

Upcoming Work Planned Next Week

  • Complete storm sewer installation in Phase 3 on Scottswood (East).
  • Complete Fairbank storm sewer installation. (Phase 2)
  • Begin con...
Read on...

Construction Updates Construction Updates
Posted on: June 30, 2017

New Traffic Patterns and Detours!

Construction Map 6-29-2017

Effective July 5, 2017, weather permitting, new traffic patterns and detours will be established in and around the Village of Riverside.

For the next phase of the MWRD Salt Creek Intercepting Sewer Rehabilitation Project, Kenny Construction will be working...

Read on...

Construction Detour Map Construction Updates
Posted on: June 30, 2017

Project Update: First Division Sewer Separation - June 30, 2017

Work Completed This Past Week

  • Asphalt patching was completed in Phase 1 limits.
  • Sod restoration was completed in Phase 1 limits.
  • Phase 2 storm sewer was installed to Scottswood Common.
  • Pavement patching was completed on Barrypoint. Barrypoint Detour was remov...
Read on...

Additional Info... Construction Updates
Posted on: June 23, 2017

Project Update: First Division Sewer Separation - June 23, 2017

First Division Sewer Separation Project - Progress Report

June 23, 2017

Work Completed This Past Week

  • Storm sewer installation continued along Fairbank and Barrypoint in Phase 2 project limits.
  • Barrypoint Detour was installed.
  • Asphalt patching restora...
Read on...

Construction Updates
Posted on: June 16, 2017

Project Update: Train Station Roof Replacement

Clay roof tiles have been removed.  Tiles suitable for reuse have been stored and replacement tiles have been ordered from the manufacturer.  The projected delivery of replacement tiles is August.  New valley flashings have been...

Read on...

Construction Updates
Posted on: June 16, 2017

Project Update: First Division Sewer Separation

Entire Construction Area:

  • All trees within construction limits have been pruned as needed.
  • Tree protection has been established.
  • Perimeter erosion barriers have been installed at the outfall locations.

Phase 1:  

  • All sanitary service and water main ad...
Read on...

Construction Updates
Posted on: June 16, 2017

Project Update: 2017 Street Improvements

Northwood:

  • Concrete saw cutting has been performed on both sides of the street.
  • Concrete curb, sidewalks, and driveway aprons on both sides of the street have been removed.

Evelyn:

  • Concrete saw cutting has been performed on both sides of the street.
  • Concrete c...
Read on...

Additional information. Construction Updates
Posted on: June 9, 2017

Weekly Construction Update - June 9, 2017

First Division Sewer Separation Project

Progress Report

June 9, 2017

Work Completed This Past Week

  • Contractor completed installation of new storm sewer within Phase 1.
  • Contractor began installation of new storm in Phase 2 starting with the installation of the ...
Read on...

Construction Updates
Posted on: May 26, 2017

Weekly Construction Update - May 26, 2017

First Division Sewer Separation Project

Progress Report

May 26, 2017

Work Completed This Past Week

  • Contractor continued sanitary service replacements within Phase 1 limits.
  • Contractor completed installation of sanitary manholes and connections within Phase 1.
  • C...
Read on...

Construction Updates
Posted on: May 24, 2017

Forest Avenue Update

Mollies Public House - Forest Avenue

Forest Avenue has reopened to two-way traffic and parking is now available on both sides of the street.

The MWRD project has relocated to Riverside Road.  Please use caution when crossing the BNSF railroad tracks in the center of town. Traffic is ...

Read on...

Construction Updates
Posted on: May 19, 2017

1st Division Sewer Separation Project Update

First Division Sewer Separation Project

Progress Report

May 19, 2017

Work Completed This Past Week

  • Contractor continued sanitary service replacements within Phase 1 limits.
  • Contractor began installation of new sanitary manholes and new storm sewer line within ...
Read on...

Construction Updates
Posted on: May 12, 2017

Weekly Construction Update - May 12

Road-closed-signs-detour-traffic

First Division Sewer Separation Project - Progress Report - May 12, 2017

Work Completed This Week

  • Contractor completed installation of tree protection fencing.
  • Contractor began installations of sanitary service adjustments and replacements ...
Read on...

Construction Updates
Posted on: May 10, 2017

Construction Update - May 10

Road-closed-signs-detour-traffic

Pavement striping on Quincy and Longcommon will be installed May 10th.  Please allow additional time and utilize caution while driving in the area and obey any posted no parking or temporary detours signs and any flaggers.  The stamped a...

Read on...

Construction Updates
Posted on: May 5, 2017

Weekly Construction Update - May 5

First Division Sewer Separation Project

Progress Report

May 5, 2017

Work Completed This Past Week

  • Contractor installed perimeter erosion barrier along four outfall work areas.
  • Contractor removed trees, canopy pruned trees, and root pruned trees.
  • Contractor inst...
Read on...

Construction Updates
Posted on: April 27, 2017

2017 Construction Projects

Various large scale construction projects are underway this year in and around Riverside including Village, MWRD and IDOT projects. For details on these various projects see below.

FIRST DIVISION SEWER SEPARATION PROJECT – VILLAGE OF RIVERSIDE 

Thi...

Read on...

Construction Updates