News Flash

Posted on: June 14, 2019

Metra Pedestrian Access Update June 14, 2019

Metra PAIP Brick Work - 6-14-2019

Work Completed This Week

  • JE Landworks placed and fine graded sand for brick pavers.
  • JE Landworks began setting brick pavers

Upcoming Work Planned for Next Week

  • D Construction will begin masonry work for the planter. 
  • JE Landworks will continue to inst...
Read on...

View All Updates Here Construction Updates
Posted on: June 14, 2019

Street Paving Update - June 14, 2019

Forest Avenue Sidewalk Work - 6-14-2019

Work Completed this Week

  • Finished pouring concrete sidewalks and ADA ramps on Herrick Road
  • Finished pouring concrete sidewalks, ADA ramps and curb/gutter on Forest Avenue
  • Poured concrete sidewalks, ADA ramps and curb/gutter on Barrypoint Road
  • Removed and pour...
Read on...

View All Updates Here Construction Updates
Posted on: June 7, 2019

Metra Pedestrian Access Update June 7, 2019

Metra PAIP Concrete Work - 6-7-2019

Work Completed this Week

  • D Construction completed a sewer repair on the south side of Bloomingbank Road.
  • D Construction placed and graded stone sub-base for brick pavers along the west side of Bloomingbank Road.
  • Carrera Concrete framed and poured concrete cu...
Read on...

View All Updates Here Construction Updates
Posted on: June 7, 2019

Street Paving Update - June 7, 2019

Herrick Road Repaving Photo - 6-7-2019

Work Completed this Week

  • Poured concrete driveway on Herrick Road at St. Mary Church
  • Poured concrete sidewalks and ADA ramps on Herrick Road
  • Poured concrete curb & gutter along Forest Avenue
  • Poured concrete sidewalks and ADA ramps along Forest Avenue
  • Remov...
Read on...

View All Updates Here Construction Updates
Posted on: May 31, 2019

Metra Pedestrian Access Update May 31, 2019

MPAIP Excavation Photo - 5-31-2019

Work Completed this Week

  • Carrera Concrete constructed new curb and gutter and exposed aggregate sidewalk on Bloomingbank Road.
  • D Construction framed, installed rebar and poured concrete yhe footing for the masonry wall planter at the southwest quadrant of B...
Read on...

View All Updates Here Construction Updates
Posted on: May 31, 2019

Street Paving Update - May 31, 2019

Herrick Road Repaving Photo - 5-31-2019

Work Completed this Week

  • Poured concrete curb & gutter along Herrick Road
  • Poured concrete ADA ramps at intersection of Herrick Road & Cowley Road
  • Poured concrete sidewalk along Herrick Road
  • Removed remaining sidewalk, curb & gutter and 1 driveway ...
Read on...

View All Updates Here Construction Updates
Posted on: May 24, 2019

Street Paving Update - May 24, 2019

Herrick Road Repaving Photo - 5-24-2019

Work Completed this Week

  • Removed sidewalk, curb & gutter on Herrick Road
  • Removed existing ADA ramps at intersection of Herrick Road & Cowley Road

Upcoming Work Planned Next Week

  • Pour concrete curb & gutter along Herrick Road
  • Pour concrete ADA ramps...
Read on...

View All Updates Here Construction Updates
Posted on: May 24, 2019

Commuter Lot 1 Construction Update - May 24, 2019

5-10-2019 Paver Completion

Work was substantially completed and the lot was opened to the public on Friday, May 17.  Remaining work to be completed includes installation of the permanent light poles and miscellaneous punch list work. 

Read on...

View All Updates Here Construction Updates
Posted on: May 24, 2019

Metra Pedestrian Access Update May 24, 2019

Metra Pedestrian Access Excavation - 5-24-2019

Work Completed this Week

  • Storm sewer improvements were completed on Bloomingbank Road.
  • Pavement, curb and gutter, and sidewalk removals were completed on Bloomingbank Road.

Upcoming Work Planned Next Week

  • Excavate dirt and place sub-base stone at the curb &am...
Read on...

View All Updates Here Construction Updates
Posted on: May 17, 2019

Street Paving Update - May 17, 2019

Herrick Road Repaving Photo - 4-26-2019

Work Completed this Week

  • There was no work on this project during the past week.

Upcoming Work Planned for Next Week

  • Removing curb & gutter on Herrick Road.
  • Removing existing ADA ramps at Herrick Road & Cowley Road.
Read on...

View All Updates Here Construction Updates
Posted on: May 10, 2019

Commuter Lot 1 Construction Update - May 10, 2019

5-10-2019 Paver Completion

Work Completed this Week

  • Completed permeable paver installation and inlaid pavement markings.
  • Installed remaining concrete sidewalk and driveway pavements.
  • Installed span wire for parking sign installation.

Upcoming Work Planned Next Week

  • Install plantings and...
Read on...

View All Updates Here Construction Updates
Posted on: May 9, 2019

Construction Notice - Metra Pedestrian Access Project

Metra Pedestrian Access Improvements Snip for Trending

The Metra Pedestrian Access Improvement Project is scheduled to begin on Monday, May 13, 2019.  The project consists of reconstructing the intersection at Riverside Road and Bloomingbank Road, installing brick paver pedestrian walkways, bicycle r...

Read on...

Learn more about the project here. Construction Updates
Posted on: May 3, 2019

Commuter Lot 1 Construction Update - May 3, 2019

5-3-2019 - Lot 1 Pavers 1

Work Completed this Week

  • Continued brick paver installation.
  • Installed brick paver parking striping.
  • Removed curb and sidewalk in preparation for concrete installation.

Upcoming Work Planned Next Week

  • Begin installing plantings in rain garden (weather permitti...
Read on...

View All Updates Here Construction Updates
Posted on: April 26, 2019

Commuter Lot 1 Construction Update - April 26, 2019

4-23-2019 - Pavers 6 Resized for Trending

Work Completed this Week

  • Installed small aggregate to level for brick paver installation.
  • Began brick paver installation.

Upcoming Work Planned Next Week

  • Begin installing plantings in rain garden.
  • Continue brick paver installation.
  • Install remaining concrete cu...
Read on...

View All Updates Here Construction Updates
Posted on: April 26, 2019

Street Paving Update - April 26, 2019

Herrick Road Repaving Photo - 4-26-2019

Work Completed this Week

  • Removed frames on all drainage structures to be adjusted or reconstructed on Herrick Road, Forest Avenue and Barrypoint Road.
  • Installed new catch basins and a sanitary manhole on Herrick Road.

Upcoming Work Planned Next Week

  • Sawcuttin...
Read on...

View All Updates Here Construction Updates
Posted on: April 23, 2019

Street Paving Update - April 19, 2019

Herrick Road Repaving Project Week 1 - 4-23-2019

Weekly Report #1 - April 19, 2019

Work Completed this Week

  • Mobilized to Herrick Road.
  • Investigated all existing drainage structures.
  • Sawcut removal limits for drainage structure replacement on Herrick Road and Forest Avenue.

Upcoming Work Planned Next...

Read on...

View All Updates Here Construction Updates
Posted on: April 22, 2019

Commuter Lot 1 Construction Update - April 19, 2019

Commuter Lot 1 Green Parking Lot April 16

Work Completed this Week

  • Installed final course of aggregate prior to brick paver installation with fine grading and roller compaction.
  • Installed remaining curb and gutter and concrete edge restraint within parking lot.
  • Removed sidewalk along north Bloomingb...
Read on...

View All Updates Here Construction Updates
Posted on: April 12, 2019

Commuter Lot 1 Construction Update - April 12, 2019

Rain_Garden_Parking_Lot_1_in_Progress

Work Completed this Week

  • Installed coarse aggregate subgrade in parking lot.
  • Installed remaining storm sewer and observation wells.
  • Final grade in Rain Garden 1 and Rain Garden 2.
  • Installed seed and blanket along the rain garden.
  • Began concrete curb installati...
Read on...

View All Updates Here Construction Updates
Posted on: April 5, 2019

Commuter Lot 1 Construction Update - April 5, 2019

4-5-2019 - Lot 1 Photo 3 Resized for Trending

Work Completed this Week

  • Installed electrical conduit, bollard foundations and light pole foundations.
  • Installed wire span poles and foundations.
  • Installed storm sewer and open manhole connections to the rain garden.
  • Removed existing drainage structures.

Upcom...

Read on...

View All Updates Here Construction Updates
Posted on: April 3, 2019

2019 Road Construction

Road-closed-signs-detour-traffic-temporary

The Village's 2019 street resurfacing projects are scheduled to begin on Herrick Road on April 15.   Forest Avenue and Barrypoint Road will also be resurfaced.  IDOT has awarded the resurfacing contract to Lindahl Brothers of Bensenville...

Read on...

View All Updates Here Construction Updates
Posted on: March 29, 2019

Commuter Lot 1 Construction Update

Truck-Working-Commuter-Lot-1-3-27-2019

Work Completed this Week

  • Completed removals of parking lot existing subbase down to final subgrade.
  • Completed removals and grading for subgrade elevations for Rain Garden 1 and Rain Garden 2.

Upcoming Work Planned Next Week

  • Remove existing parking lot drainag...
Read on...

View All Updates Here Construction Updates
Posted on: March 22, 2019

Commuter Lot 1 Construction Update

3-22-2019 Lot 1 Photo

Work Completed the Past Week

  • Work began on March 16, 2019.
  • Installed temporary lighting in Riverside Swim Club parking lot.
  • Installed temporary striping/numbering in Riverside Swim Club parking lot and additional train station parking.
  • Installed tree protecti...
Read on...

View All Updates Here Construction Updates