News Flash

Posted on: November 16, 2018

Construction Update - November 16, 2018

Road-closed-signs-detour-traffic-temporary

Work Completed during the Past Two Weeks (10/26/2018 to 11/16/2018)

  • New copper water service lines were installed.
  • Abandonment of the existing water main was completed.
  • Drainage structure adjustments were completed.
  • Installation of new curb and gutter, drivew...
Read on...

2018 Capital Improvements in Riverside Construction Updates
Posted on: October 26, 2018

Construction Update - October 26

Road-closed-signs-detour-traffic-temporary

Train Depot Rehabilitation Project

Progress Report 4

October 26, 2018

Work Completed Past Week (10/19/2018 to 10/26/2018) 

Percentage Work Completed: 97%

  • Skim coating of the retaining wall adjacent to the North platform parking lot was completed.
  • Insta...
Read on...

2018 Capital Improvements in Riverside Construction Updates
Posted on: October 26, 2018

Construction Update - October 26

Road-closed-signs-detour-traffic-temporary

2018 Water Main Improvements

PHASE 1:  Northgate Court

Progress Report 1

October 26, 2018

 

Work Completed to Date (10/17/2018 to 10/26/2018)

  • Contractor commenced work on Northgate Ct. on October 17, 2018
  • Installation of new ductile iron water ...
Read on...

2018 Capital Improvements in Riverside Construction Updates
Posted on: July 5, 2018

Weekly Construction Update - July 5, 2018

Road-closed-signs-detour-traffic-temporary

Work Completed the Past Week

  • Binder asphalt installed on the 100 Block of Fairbank.
  • Drainage structure adjustments made on Fairbank and Scottswood Roads.
  • Completed all concrete work.

Upcoming Work Planned the Next Two Weeks

  • Roadway preparation for paving.
  • Finis...
Read on...

2018 Capital Improvements in Riverside Construction Updates
Posted on: June 28, 2018

Weekly Construction Update - June 28, 2018

Road-closed-signs-detour-traffic-temporary

Work Completed the Past Week

  • Roadway level binder installation completed throughout First Division.
  • Milled pavement on 100 Block Fairbank Road.
    • Road is closed, local traffic only.

Upcoming Work Planned the Next Two Weeks

  • 100 Block of Fairbank Road Reconstructi...
Read on...

2018 Capital Improvements in Riverside Construction Updates
Posted on: June 20, 2018

Weekly Construction Update - June 20, 2018

Road-closed-signs-detour-traffic-temporary

Work Completed the Past Week

  • Roadway asphalt patching.
  • Preparing roadway for level binder (Fairbank/Coonley/Scottswood)

 

Upcoming Work Planned the Next Two Weeks

  • Install leveling binder. Beginning on Fairbank (200-400 Blocks) on 6/21/18 (weather perm...
Read on...

2018 Capital Improvements in Riverside Construction Updates
Posted on: May 9, 2018

Construction Projects Begin Tomorrow

Road-closed-signs-detour-traffic-temporary

MWRD Salt Creek Intercepting Sewer Relining Project:  Kenny Construction will begin mobilizing for a project re-start on Thursday, May 10. Mobilization will include implementing traffic control, detours and tent set-up on Riverside Road south of ...

Read on...

View the First Division Construction Notice here. Construction Updates
Posted on: June 12, 2018

Weekly Construction Update - June 12, 2018

Road closed signs detour traffic

Work Completed the Past Two Weeks

  • Sewer structure replacements and reconstructions have been completed.
  • Roadway grinding operations have been completed.

Upcoming Work Planned the Next Two Weeks

  • Roadway asphalt patching.
    • Impacted residents will receive notices ...
Read on...

2018 Capital Improvements in Riverside Construction Updates