[ARCHIVED] Weekly Construction Update - July 5, 2018

Road-closed-signs-detour-traffic-temporary

Work Completed the Past Week

  • Binder asphalt installed on the 100 Block of Fairbank.
  • Drainage structure adjustments made on Fairbank and Scottswood Roads.
  • Completed all concrete work.

Upcoming Work Planned the Next Two Weeks

  • Roadway preparation for paving.
  • Finish drainage structure adjustments.
  • Begin surface asphalt paving operations on July 9. Fresh oil will be installed the morning of July 9. Residents should drive nor more than 10 MPH in areas where “Fresh Oil” signs are present. No Parking signs will be installed.
  • Begin landscaping.