PHASE 1: Northgate Court
Progress Report 1
October 26, 2018
Work Completed to Date (10/17/2018 to 10/26/2018)
- Contractor commenced work on Northgate Ct. on October 17, 2018
- Installation of new ductile iron water main 8”, was completed.
- Pressure and water leakage tests on the new water main were successfully completed.
- Chlorination of the new water main was completed.
Upcoming Work Planned (10/29/2018 to 11/2/2018)
- New water copper service lines, with new curb stops and Buffalo service boxes will be completed by the end of the week.
- Abandonment of the existing water main will be completed by the end of the week.