Work Completed this Week
- Removed frames on all drainage structures to be adjusted or reconstructed on Herrick Road, Forest Avenue and Barrypoint Road.
- Installed new catch basins and a sanitary manhole on Herrick Road.
Upcoming Work Planned Next Week
- Sawcutting curb & gutter removal limits on Herrick Road, Forest Avenue and Barrypoint Road.
- Removing curb & gutter on Herrick Road.
- Removing existing ADA ramps at Herrick Road and Cowley Road.
- Removing and replacing catch basins and sanitary manholes on Forest Avenue.