[ARCHIVED] Construction Update - May 10, 2019

5-10-2019 Paver Completion

Work Completed this Week

  • Completed permeable paver installation and inlaid pavement markings.
  • Installed remaining concrete sidewalk and driveway pavements.
  • Installed span wire for parking sign installation.

Upcoming Work Planned Next Week

  • Install plantings and mulch in rain gardens.
  • Complete permeable paver chip filler installation and punch list.
  • Install sign foundations and posts.
  • Install parking, handicap, educational, and information signs within Commuter Lot #1.
  • Install remaining seed and blanket around perimeter of parking lot.
  • Remove tree protection and fencing.

View All Updates Here
Facebook Twitter Email

Other News in E-Flash

Santas Mailbox

Santa's Mailbox is Back!

Posted on: November 22, 2023
Fall Leaves

Leave the Leaves this Fall

Posted on: November 24, 2023
Shot to a sewer at the edge of sidewalk

Sewer Repairs Rescheduled to Tomorrow

Posted on: November 21, 2023
Riverside Logo framed square standard

Village's Tax Levy

Posted on: November 11, 2023
Credit Rating Graphic_resized

Village's AA+ Credit Rating Reaffirmed

Posted on: November 3, 2023
Close up back side of new silver car parking on the asphalt road

Vehicle Stickers and Pet Tags Reminder

Posted on: October 27, 2023
Halloween tower

Fall/Winter Brochure Available Now!

Posted on: September 25, 2023
Road closed signs detour traffic

Road Projects: Frequently Asked Questions

Posted on: September 6, 2023
no-soliciting-traffic-street-sign

Door to Door Solicitation List

Posted on: July 15, 2023