Construction Updates

Posted on: May 31, 2019

[ARCHIVED] Metra Pedestrian Access Update May 31, 2019

MPAIP Excavation Photo - 5-31-2019

Work Completed this Week

  • Carrera Concrete constructed new curb and gutter and exposed aggregate sidewalk on Bloomingbank Road.
  • D Construction framed, installed rebar and poured concrete yhe footing for the masonry wall planter at the southwest quadrant of Bloomingbank Road and the BNSF Railroad tracks. 
  • D Construction placed sub-base stone for new brick pavers along north Bloomingbank Road. 

Upcoming Work Planned Next Week

  • D Construction will continue backfilling and placing sub-base stone for new brick pavers along north Bloomingbank Road.
  • JE Landworks will begin brick paver installation.
  • Carrera Concrete will complete curb and gutter and sidewalk along the north side of Bloomingbank Road.
  • Edmund & Nelson will begin installing electrical on the north side of Bloomingbank Road. 