Work Completed this Week
- Finished pouring concrete sidewalks and ADA ramps on Herrick Road
- Finished pouring concrete sidewalks, ADA ramps and curb/gutter on Forest Avenue
- Poured concrete sidewalks, ADA ramps and curb/gutter on Barrypoint Road
- Removed and poured concrete Metra lot driveway #2
Upcoming Work Planned for Next Week
- Pour remaining sidewalks, curb/gutter and ADA ramps on Barrypoint Road
- Mill existing pavement on Herrick Road, Forest Avenue and Barrypoint Road
- Begin pavement patching and sewer structure adjustments on Herrick Road, Forest Avenue and Barrypoint Road