Work Completed this Week
- Completed backfilling gap between new curb and existing pavement with stone on North side of Selborne Road
- Opened all driveways for access on North side of Selborne Road
- Saw cut pavement on South side of Selborne Road
- Began removal of existing curb and gutter and driveway aprons on South side of Selborne Road
- Began grading for curb and gutter installation on South side of Selborne Road
Upcoming Work Planned for Next Week
- Complete removal of curb and gutter and driveway aprons on South side of Selborne Road
- Adjust drainage structures on South side of Selborne Road
- Begin installation of curb and gutter on South side of Selborne Road
- Begin preparation for concrete driveway aprons on South side of Selborne Road