Work Completed this Week
- Adjusted drainage structures on South side of Selborne Road
- Completed installation of new concrete curb and gutter on South side of Selborne Road
- Began framing for driveway aprons on South side of Selborne Road
Upcoming Work Planned Next Week
- Complete installation of driveway aprons on Selborne Road
- Complete all ADA ramps and miscellaneous exposed aggregate sidewalk on South side of Selborne Road
- Backfill gap between existing pavement and new curb and gutter with stone on South side of Selborne Road
- Open all driveway aprons for access on South side of Selborne Road