5-22-2020 Curb and Gutter Resized for Trending

Work Completed this Week

  • Adjusted drainage structures on South side of Selborne Road
  • Completed installation of new concrete curb and gutter on South side of Selborne Road
  • Began framing for driveway aprons on South side of Selborne Road

Upcoming Work Planned Next Week

  • Complete installation of driveway aprons on Selborne Road
  • Complete all ADA ramps and miscellaneous exposed aggregate sidewalk on South side of Selborne Road
  • Backfill gap between existing pavement and new curb and gutter with stone on South side of Selborne Road
  • Open all driveway aprons for access on South side of Selborne Road

See All Construction Updates Here