Posted on: May 22, 2020

[ARCHIVED] Selborne Road Construction Update for May 22

5-22-2020 Curb and Gutter Resized for Trending

Work Completed this Week

  • Adjusted drainage structures on South side of Selborne Road
  • Completed installation of new concrete curb and gutter on South side of Selborne Road
  • Began framing for driveway aprons on South side of Selborne Road

Upcoming Work Planned Next Week

  • Complete installation of driveway aprons on Selborne Road
  • Complete all ADA ramps and miscellaneous exposed aggregate sidewalk on South side of Selborne Road
  • Backfill gap between existing pavement and new curb and gutter with stone on South side of Selborne Road
  • Open all driveway aprons for access on South side of Selborne Road

See All Construction Updates Here
Facebook Twitter Email

Other News in E-Flash

Santas Mailbox

Santa's Mailbox is Back!

Posted on: November 22, 2023
Fall Leaves

Leave the Leaves this Fall

Posted on: November 24, 2023
Shot to a sewer at the edge of sidewalk

Sewer Repairs Rescheduled to Tomorrow

Posted on: November 21, 2023
Riverside Logo framed square standard

Village's Tax Levy

Posted on: November 11, 2023
Credit Rating Graphic_resized

Village's AA+ Credit Rating Reaffirmed

Posted on: November 3, 2023
Close up back side of new silver car parking on the asphalt road

Vehicle Stickers and Pet Tags Reminder

Posted on: October 27, 2023
Halloween tower

Fall/Winter Brochure Available Now!

Posted on: September 25, 2023
Road closed signs detour traffic

Road Projects: Frequently Asked Questions

Posted on: September 6, 2023
no-soliciting-traffic-street-sign

Door to Door Solicitation List

Posted on: July 15, 2023