Construction Updates

Posted on: June 26, 2020

[ARCHIVED] Selborne Road Construction Update for June 26

Selborne Road Asphalt Paving 6-26-2020

Work Completed this Week

  • Completed fine grading aggregate stone base on Selborne Road
  • Placed 3.5 inches of hot mix asphalt binder course on Selborne Road
  • Placed 1 inch of hot mix asphalt leveling binder course on Parkway Road
  • Began adjusting manhole frames to finish grade on Selborne Road

Upcoming Work Planned Next Week

  • Complete adjusting manholes frames to finish grade on Selborne Road
  • Pave the final 1.5" layer of hot mix asphalt surface course on Selborne Road and on Parkway Road