Work Completed this Week
- Completed fine grading aggregate stone base on Selborne Road
- Placed 3.5 inches of hot mix asphalt binder course on Selborne Road
- Placed 1 inch of hot mix asphalt leveling binder course on Parkway Road
- Began adjusting manhole frames to finish grade on Selborne Road
Upcoming Work Planned Next Week
- Complete adjusting manholes frames to finish grade on Selborne Road
- Pave the final 1.5" layer of hot mix asphalt surface course on Selborne Road and on Parkway Road