Work Completed this Week
- Completed adjusting manholes frames to finish grade on Selborne Road and Parkway Road
- Completed paving the final layer (1.5 inches) of hot mix asphalt surface course on Selborne Road and Parkway Road
Upcoming Work Planned Next Two Weeks
- Landscape restoration (preparation for topsoil, seed, and blanket) will begin on Selborne Road and Parkway Road
- Brick pavers which were removed due to installation of new curb and gutter will be reset at existing driveway aprons on Selborne Road
- Punch list items pertaining to road reconstruction/paving will be identified
- Thermoplastic pavement markings (stop bars/crossing) will be installed where applicable on Selborne Road and Parkway Road
- General site clean up