Work Completed this Week
- Excavating to subgrade, placing geo-grid fabric, and placing stone base on Selborne Road (Lindberg Road going north to Kent Rd)
- Pouring concrete for curb & gutter on Selborne Road (York Rd to Lindberg Rd)
- Pouring concrete for sidewalk on Selborne Road (York Rd to Longcommon Rd- various locations)
Upcoming Work Planned Next Week
- Remove pavement, excavate dirt, place geo-grid fabric, and place stone base on Selborne Road (Lindberg Rd to Longcommon Road)
- Complete pouring of concrete for curb & gutter on Selborne Road (York Rd to Kent Rd-various locations)
- Complete pouring of concrete for driveways on Selborne Road (York Rd to Lindberg Rd)
Questions or Concerns
The Village of Riverside is aware of the disruption and inconvenience this project will cause and appreciates your patience and cooperation. If you have any questions or concerns, please feel free to call the Resident Engineer, Scott Soderstrom at (224) 240-2998, Project Manager Orion Galey at (847) 833-0210, or the Public Works Department at (708) 442-3590.
Updates will be provided via e-flash, Facebook and Twitter.