Selborne Road Reconstruction Project Update
Work Completed this Week (10/31-11/4)
- Contractor completed removing pavement, excavating dirt, placing geo-grid fabric, and placing stone base on Selborne Road (Lindberg Rd to Longcommon Road)
- Contractor completed the pouring of the concrete for curb & gutter on Selborne Road (York Rd to Kent Rd-various locations)
- Contractor completed the pouring of concrete for driveways on Selborne Road (York Rd to Lindberg Rd)
Upcoming Work Planned Next Week
- Contractor to add stone and fine grade the stone base on Selborne Road (York Rd to Longcommon Rd)
- Contractor to place the 1st layer of asphalt on Selborne Road (York Rd to Longcommon Rd)
- to start excavating soil and placing the stone base for the new sidewalk in Turtle Park