First Division Sewer Separation Project

Progress Report

May 19, 2017

Work Completed This Past Week

  • Contractor continued sanitary service replacements within Phase 1 limits.
  • Contractor began installation of new sanitary manholes and new storm sewer line within Phase 1.
  • Contractor adjusted watermain at Millbridge and Scottswood intersection on Millbridge.

Upcoming Work Planned Next Week

  • Contractor will continue sanitary service adjustments and replacements within Phase 1 limits.
  • Contractor will continue installation of new storm and sanitary sewer within Phase 1.

Read the full Construction Notice here.  

View or download the Project Map here.