First Division Sewer Separation Project
Progress Report
June 9, 2017
Work Completed This Past Week
- Contractor completed installation of new storm sewer within Phase 1.
- Contractor began installation of new storm in Phase 2 starting with the installation of the new outfall at the Des Plaines River.
- Jetted trenches in Phase 1 project limits.
Upcoming Work Planned Next Week
- Contractor will begin restoration within Phase 1 limits, including concrete restoration.
- Contractor will continue storm sewer installation within Phase 2 limits along Fairbank.