First Division Sewer Separation Project - Progress Report
June 23, 2017
Work Completed This Past Week
- Storm sewer installation continued along Fairbank and Barrypoint in Phase 2 project limits.
- Barrypoint Detour was installed.
- Asphalt patching restoration in Phase 1 began.
- Concrete restoration in Phase 1 limits was completed.
- Phase 3 sanitary sewer installation was completed on Scottswood (East)
Upcoming Work Planned Next Week
- Contractor will complete asphalt patching Phase 1 limits.
- Preparation for sod installation will begin in Phase 1.
- Contractor will continue Phase 2 storm sewer installation along Barry Point Rd. A detour for traffic on Barrypoint will be active.
- Storm sewer installation will be completed on Fairbank in Phase 2 limits.