News Flash

Posted on: November 23, 2022

Construction Update November 23, 2022

Selborne 11-23 1

Work Completed this Week

  • Contractor placed the final layer of asphalt (surface course) on Selborne Road (York Rd to Longcommon Rd)
  • Contractor removed and replaced sidewalk at various locations in Riverside
  • Seasonal Concepts placed topsoil for sod on Selborne...
Read on...

E-Flash
Posted on: November 22, 2022

Street Improvement Program Update

Selborne 11-18 2

In an effort to achieve the most economical pricing from contractors, the Village typically plans sidewalk repairs in conjunction with the annual Street Improvements Program. The 2022 Streets Program utilized Motor Fuel Tax and Rebuild Illinois bond proce...

Read on...

E-Flash
Posted on: November 18, 2022

Construction Update November 18, 2022

Selborne 11-18 2

Work Completed this Week

  • Contractor paved the 1st layer (binder course) of asphalt on Selborne Road (York Rd to Longcommon Rd)
  • Contractor poured concrete for the new sidewalk in Turtle Park
  • Seasonal Concepts started landscaping (topsoil placement) on Selborn...
Read on...

E-Flash
Posted on: November 11, 2022

Selborne Road Reconstruction Project Update November 11, 2022

Selborne 11-11 1

Work Completed this Week

  • Contractor added stone and fine graded the stone base on Selborne Road (York Rd to Longcommon Rd)
  • Contractor excavated soil and placing the stone base for the new sidewalk in Turtle Park
  • Contractor framed for the new sidewalk in Turt...
Read on...

E-Flash
Posted on: November 11, 2022

Selborne Road asphalt paving to occur tomorrow, November 12

Construction Advisory - V01

CONSTRUCTION NOTICE

Selborne Rd and Kent Rd 

Reconstruction Project

Asphalt Paving Notification

Tomorrow, Saturday, November 12th, paving of the first layer of asphalt (binder course) will be completed on both Selborne Rd (Longcommon Rd to York Rd) a...

Read on...

E-Flash
Posted on: November 4, 2022

Selborne Road Project Update November 4, 2022

Selborne 11-4-2

Selborne Road Reconstruction Project Update

 

Work Completed this Week (10/31-11/4)

  • Contractor completed removing pavement, excavating dirt, placing geo-grid fabric, and placing stone base on Selborne Road (Lindberg Rd to Longcommon Road)
  • Contractor ...
Read on...

E-Flash
Posted on: October 28, 2022

Selborne Road Project Update October 28, 2022

Selborne 10-28-2

Work Completed this Week

  • Excavating to subgrade, placing geo-grid fabric, and placing stone base on Selborne Road (Lindberg Road going north to Kent Rd)  
  • Pouring concrete for curb & gutter on Selborne Road (York Rd to Lindberg Rd)
  • Pouring concr...
Read on...

E-Flash
Posted on: October 14, 2022

Selborne Road Project Update October 14, 2022

Selborne Road 1

Work Completed this Week

  • M & J saw cutting removal limits on Selborne Road (York Rd to Longcommon Rd)
  • M & J removing pavement, curb & gutter, driveways, and misc. sidewalk on Selborne Road (York Rd going north toward Lindberg Rd)
  • M & J instal...
Read on...

E-Flash
Posted on: October 10, 2022

Selborne Road Update October 10, 2022

Selborne Road progress 2022

The Selborne Road and Kent Road paving project is moving forward. Last week the following work was completed: 

  • Seasonal Concepts installed tree protective fence at Selborne Road and Turtle Park area.
  • Seasonal Concepts pruned trees at various locati...
Read on...

E-Flash
Posted on: October 10, 2022

ComEd to begin infrastructure improvements along Village streets today, October 10

Power-Outage

ComEd will begin infrastructure improvements along Barrypoint, Burling, Fairbank and Scottswood roads today, October 10. Please exercise caution while in the area.

E-Flash
Posted on: September 7, 2022

Parking Restrictions: Pavement Rejuvenation to take place late Thursday evening, September 8

Road closed signs detour traffic

The Village’s contractor, Professional Paving & Concrete Company, will be applying pavement rejuvenation starting late Thursday night September 8th. Operations will be conducted overnight to limit the impact to residents and commuters. The roads invol...

Read on...

E-Flash
Posted on: August 9, 2022

Groveland Avenue Road Work

Road-closed-signs-detour-traffic-temporary

Groveland Avenue will closed to all through traffic today, August 9 as crews will be completing road work. Work will continue over the next few days, but the road should be reopened to through traffic tomorrow, August 10. Certain portions may remain barri...

Read on...

E-Flash
Posted on: June 17, 2022

No Parking on Gage and Olmsted Roads tomorrow, June 18

No Parking

Crews will be removing brush on Gage and Olmsted Roads. There will be no parking from 7:00 a.m. to 6:00 p.m. tomorrow.

E-Flash
Posted on: May 6, 2022

Debris Under Forest Avenue Bridge

Forest Avenue Bridge Debris

The Village of Riverside is aware of the substantial debris that has accumulated by the Forest Avenue bridge due to the heavy rains. We have contacted Metropolitan Water Reclamation District (MWRD) and Illinois Department of Transportation (IDOT), as they...

Read on...

E-Flash